Holston River Debris Removal

Project Type:

Bridge Debris Removal

Service Area:

Marine Construction

Market:

Transportation

Location:

Knoxville, Tennessee

Overview:

We removed accumulated timber debris around in-water concrete bridge piers using a floating barge platform. Our team delivered, assembled, and positioned the barge sections in the water before walking an excavator onto the platform, moving it into position, and removing the debris from the bridge site. This approach required more preparation than staging the removal from the bridge deck. However, it was selected because it provided an efficient means for clearing the debris without closing traffic lanes on the bridge. In total, approximately 314 cubic yards of debris were removed.